EIA Notification / AUTHORITIES/ State Pollution Control Board
State Pollution Control Board
|
The SPCB’s role is in the public consultation stage of the Environment Clearance process. The public hearing at, or in close proximity to, the site(s) in all cases is to be conducted by the State Pollution Control Board (SPCB) or the Union Territory Pollution Control Committee (UTPCC) concerned in the specified manner and forward the proceedings to the regulatory authority concerned within 45 (forty five) of a request to the effect from the applicant.
Section 7.III.iii
In case the State Pollution Control Board or the Union territory Pollution Control Committee concerned does not undertake and complete the public hearing within the specified period, and/or does not convey the proceedings of the public hearing within the prescribed period directly to the regulatory authority concerned as above, the regulatory authority shall engage another public agency or authority which is not subordinate to the regulatory authority, to complete the process within a further period of forty five days
Section 7.III.iv
For obtaining responses in writing from other concerned persons having a plausible stake in the environmental aspects of the project or activity, the concerned regulatory authority and the State Pollution Control Board (SPCB) or the Union territory Pollution Control Committee (UTPCC) shall invite responses from such concerned persons by placing on their website the Summary EIA report
Section 7.III.vi
The step wise role of the SPCB/UTPCC in the public consultation process is given in Appendix IV